Close Menu
Straightnews

    Subscribe to Updates

    Get the latest creative news from FooBar about art, design and business.

    What's Hot

    AFCON 2025: Nigeria claim bronze medal After Crushing Egypt on Penalties

    January 17, 2026 --- 9:02 pm

    Consortium Plans to Invest $8 billion in Ibom Deep Seaport

    January 16, 2026 --- 9:02 pm

    Two Scholars Take on Akwa Ibom AG over Stubbs Creek Land Ownership  

    January 16, 2026 --- 4:01 pm
    Facebook X (Twitter) Instagram
    Trending
    • AFCON 2025: Nigeria claim bronze medal After Crushing Egypt on Penalties
    • Consortium Plans to Invest $8 billion in Ibom Deep Seaport
    • Two Scholars Take on Akwa Ibom AG over Stubbs Creek Land Ownership  
    • Reframing Nigeria’s Banditry Crisis: From Assumptions to Reasons
    • Inauguration: Catholic Knight Quits over Alleged Non-Acknowledgement of Ubah
    • Be catalysts for Positive change- Clergyman tasks Christians
    • FG, ASUU Seal New Deal with 40% Emolument for University Lecturers
    • Another Newswatch Magazine co-founder Yakubu Mohammed dies
    Facebook X (Twitter) Instagram
    Straightnews
    • Home
    • About Us
      • About StraightNews
      • Our Philosophy
      • Editorial Board
    • News
      • Nationwide News
      • Community News
      • Regional News
        • North Central
        • North East
        • North West
        • South East
        • South South
        • South West
    • Nigeria
      • Politics
      • Economy
      • Education
      • Security
      • Energy
      • Agriculture
      • Health
      • Labour
      • Environment
      • Technology
      • Real Estate
      • Transportation
      • Judiciary
      • Electricity
    • Foreign
      • Africa
        • West Africa
        • South Africa
        • North Africa
        • East Africa
      • America
      • Asia
      • Europe
    • Social
      • Photo Gallery
      • Entertainment
      • Events
      • Fashion
      • Fitness
      • Short Stories
      • Lifestyle
      • Relationship
      • Travel
      • Specials
        • Personality Interview
        • Special Reports
        • Profile
    • Articles
      • Editorial
      • Opinion
      • Essay
    • Contact Us
    • Sports
    Straightnews
    Home»Government»Exclusive: Akwa Ibom Spent N55.3b On Roads In 2019
    Government

    Exclusive: Akwa Ibom Spent N55.3b On Roads In 2019

    straightnewsng.comBy straightnewsng.comNovember 18, 2020 --- 10:56 pmUpdated:September 27, 2022 --- 11:47 amNo Comments10 Mins Read
    WhatsApp Facebook Twitter Pinterest LinkedIn Tumblr Email
    Road straightnews
    Road
    Share
    WhatsApp Facebook Twitter LinkedIn Pinterest Email

    On completion of his first term in office, Akwa Ibom Governor Udom Emmanuel rolled out “Completion Agenda” that commenced from May 29, 2019.

    The essence of the agenda was to serve as impetus in pushing the governor to complete development projects and programmes particularly roads undertaken in the first term.

    However, Straightnews stumbled on a publication entitled: Annual Report of the Accountant General with Audited Financial Statements for the 2019 by Office of the state Accountant-General, Pastor Uwem S. Andrew-Essien, detailing the expenditure profile of the government.

    A cursory look at the publication shows that Akwa Ibom government paid various sums of money through the state Ministry of Works to contractors for the execution of road project spread across many local government areas in the state.

    Of N80,226,146,500 approved by the state House of Assembly, the state government paid N55,327,494,887 or 69 per cent of the budgeted amount for construction of roads last year. The variance was N27,398,651,703 or 34.2 per cent of the overall.

    Details of the Expenditure Profile

    Details of the Expenditure Profile

    S/NO. Name of Road Budget Actual Variance
    1 Construction of 12.1km Ikot Akpan Abia-Oboyo Ikot Ika-Enen Nsit Rd in Nsit Ibom L.G.A. 1,000,000,000.00 1,000,000,000.00
    2 Construction of 12.4km Okorette-Amadaka-Kampa Road, Eastern Obolo LGA. 500,000,000.00 500,000,000.00
    3 Construction of13km Akpambiet-Edo-Edidadedo Road, Ndom Edim-Idung Akpantuen Road with Spurs and Rehabilitation 1,000,000,000.00 1,000,000,000.00
    4 Construction of 14.1km Ikpe Ikot Nkon-Obotme- Arochukwu road with 1No. bridge, Ini LGA 2,674,324,840.00 2,335,600,853.00  338,723,987.00
    5 Construction of 23.5km Ikot Ekaide-Ikot-Okoro-Ikot Ibritam Road with 2No. Bridges, Oruk Anam LGA. 2,549,723,940.00 2,549,723,940.00
    6 Construction of 24km Etebi-Enwang Road with 2No. bridges, Mbo/Esit Eket LGA. 5,000,000,000.00 862,042,165.00 4,137,957,835.00
    7 Construction of 3.5km Ring Road II from Aka Road to Abak Road under APFA, Uyo LGA. 2,782,565,670.00 916,282,833.00  1,866,282,837.000
    8 Construction of 4.2Km Abak Ifia- Ikpe Mbak Eyop- Ikot Abia Ossom- Nko Road and Spur in Ikot Ekpene/ Obot Akara LGAs 1,000,000,000.00 500,000,000.00  500,000,000.00
    9 Construction of 4.9km Ibesit Okpokoro-Ikot Ibritam Road in Oruk Anam LGA 837,522,720.00 464,394,651.00  373,128,069.00
    10 Construction of 5.0km Internal Road In Ewet Housing Estate Extension off Edet Akpan Avenue with Reclamation of flood zone and Outfall Drain(Phase I), Uyo LGA. 1,000,000,000.00 450,028,448.00  549,971,552.00
    11 Construction of 5.1km Internal Roads in Akwa Ibom State University, Obiokpa Campus and its Environs, Oruk Anam LGA. 1,094,747,490.00 329,314,739.00  765,432,751.00
    12 Construction of 6.4km Mbiaso – Nto Edino- Ikwarazu Road with 2No. Bridges, Obot Akara LGA 297,116,030.00 297,116,030.00
    13 Construction of 8.5km Nduetong Oku-Ibiaku Uruan-Ekit Itam Road and Spurs in Itu/Uruan LGAs 1,000,000,000.00 1,000,000,000.00
    14 Construction of Ikpe Junction-Obo Annang Road 1,000,000,000.00 800,132,430.00 199,867,570.00
    15 Construction of 9.0km Mbiaya Uruan-Idu-Mbiakong Uruan Road by APFA, Uruan LGA 1,000,000,000.00 1,000,000,000.00
    16. Construction of 9.5km Ikot Ebekpo-Ikot Ebidang Road in Onna LGA 2,000,000,000.00 1,087,436,160.00 912,563,840.00
    17. Construction of Awa Iman-Asong-Ikot Edim-Ikot Emem Rd with 2NO. Bridges, Onna LGA 2,490,145,900.00 2,266,270,729.00 223,875,171.00
    18. Construction of Eyotai-Ulliong-Secretariat-Edikor-Udesi Road with a Spur to the Paramount Ruler’s palace, Udung Uko LGA 2,500,000,000.00 1,491,585,839.00 1,008,414,161.00
    19 Construction of Ikot Ebiere-Ikot Edor-Ikot Iko Ibon-Okom Road and Akpabom-Ikwe Road with 15 span bridge/ 7.3 carriage (Phase 1&2), Onna LGA 2,000,000,000.00 1,002,000,000.00 998,000,000.00
    20 Construction/Remodelling of Urban Roads in Eket, Eket LGA 3,000,000,000.00 3,000,000,000.00
    21 Dualization of 19.8km Ikot Oku Ikono Junction-Etinan Road with Flyover at Ikot Oku Ikono Junction 5,000,000,000.00 2,681,112,437.00 2,318,887,563.00
    22 Dualization of 29.5km Etinan-Ndon Eyo Road with 2No. bridges and spur, Etinan/Onna LGAs 10,000,000,000.00 9,383,795,386.00 616,204,614.00
    23 Emergency works in the completion of Oron urban Roads (Additional works, Oron LGA) 2,000,000,000.00 659,981,746.00 1,340,018,254.00
    24 Dualization of Uyo-Ikot Ekpene, Uyo LGA 5,000,000,000.00 884,384,031.00 4,115,615,969.00
    25 Construction of 18.95km Ikot Ibritam-Ekeffe-Ikot Akpan Afaha Road with 2No. Bridges, Oruk Anam 2,000,000,000.00 2,000,000,000.00
    26 Construction of 9.5km Ring Road 111 from Aka Road-Nwaniba Road, Uyo LGA 5,000,000,000.00 4,008,316,683.00 991,683,317.00
    27 Construction of 29km Road from Etinan Junction to Mbioto 2 to Awa to Ndon Eyo 7,000,000,000.00 4,494,140,326.00 2,505,859,674.00
     28 Dualization of Airport-Okopedi Road with Spur 2,000,000,000.00 2,000,000,000.00
    29 Construction of 19.32km Anua-Mbak Etoi-Ishiet Road, Uyo/Uruan LGAs 1,000,000,000.00 1,000,000,000.00
    30 Construction of 14km Abak-Nsekhe-Ikot Akpa Nkuk-Ikot Etim-Ikot Ikara Road (Phase 111 section A Ikot Ibritam) Oruk Anam LGA 2,000,000,000.00 1,500,000,000.00 500,000,000.00
    31 Construction of 22km Ikot Esu-Otomo-Azumini-Ikot Ntia-Ikot Osukpong Road in Ika LGA 1,000,000,000.00 1,000,000,000.00
    32 Construction of Etinan-Ndon Eyo Road with spur 1,000,000,000.00 500,000,000.00 500,000,000.00
    33 Dualisation of Eket-Etinan Road with 3Nos. Bridges, Eket LGA 5,000,000,000.00 2,363,835,461.00 2,636,164,539.00
      Grand Total 80,226,146,590.00 55,327,494,887.00 27,398,651,703.00
    Findings: A civil engineer in the state Ministry of Works confided in Straightnews that a kilometre of road costs N300 million. The engineer who spoke on condition of anonymity said at time it could be adjusted to N303 million depending on the terrain or nature of road. “The cost includes drains, excavation of soil, stone base, asphalt, substructure, among other aspects.”

    Straightnews undertook a tour of the project sites. Though government paid N1 billion last year on the 22 kilometre-Ikot Esu-Otomo-Ikot Udom-Nto Onono-Azumini Road. Yet, the asphalted road stops at Ikot Udom Ika.

    At the stretch of a 14km Abak-Nsekhe-Ikot Akpa Nkuk-Ikot Etim-Ikot Ikara Road (Phase 111 section A Ikot Ibritam), it was confusing to fathom the exclusion of the road. It was discovered that during Chief Godswill Akpabio administration, the road was constructed by Setraco. From Abak-Nsekhe-Ikot Akpa Nkuk was constructed except that Setraco shortchanged the area by not providing drains and other appurtenances.

    Samuel Udoh from Nsekhe village was confused why the state government paid N1,500,00,000 to contractors. Except the government included Ikot Oku Usung-Ikot Udombang-Ikot Etim Road leading to Ikot Ikara Road, otherwise it looks as fraud.

    Another site was the 18.95 kilometre Ikot Ibritam-Ekeffe-Ikot Akpan Afaha Road with two bridges. The government paid N2 billion on the road to contractors last year.

    Yet, one of the sub-contractors handling the road, Tony Opara, the manager of ALMADAL NIG. LTD, was bitter at the slow pace of work done in the area. “Only three kilometers of the road have been asphalted, despite the whopping amount released.”

    The 19.32km Anua-Mbak Etoi-Ishiet Road, spanning from Uyo to Uruan Local Government Area is an eyesore. In 2019, N1 billion was paid on the road, yet various portions of the road impassable. From Mbak to Ishiet Uruan, the road is in a sorry state. Joe Effiong a resident of the road was unhappy concerning the snail-like speed of the project.

    The 9.5km Ring Road 111 from Aka Road-Nwaniba Road, Uyo LGA handled by Hensek is pitiable. Already, 4,008,316,683 was paid in 2019. The work is not commensuare with sum released to it.

    Virtually, there is no breather for all the roads. The roads are either paved or failed or abandoned or impassable even after the money has been relased.

    Performance: Despite the volume of money released, the project result is not commensurate with the amount released so far. For instance, members of Akwa Ibom State House of Assembly through their Committee on Finance and Appropriation led by Rt. Hon. Uduak Odudoh raised concerns over the spate of abandoned, dilapidated and poorly constructed roads in the state.

    During a budget defence estimate for 2020 by Ministries, Departments and Agencies (MDAs) in the state held at the Assembly complex In November 2019, the Lawmakers vented their anger over the poor state of roads.

    When the then commissioner for works, Mr. Ephraim Inyang-eyen, appeared before the committee, they observed that although a huge amount of money had been released for road infrastructural development, most of the roads constructed by Udom Emmanuel’s administration may not stay beyond the lifespan of this government.

    Leading the probe was a first timer in the 7th Assembly and member representing Mkpat Enin State Constituency who serves as Chairman Judiciary, Justice, Public Petition and Human Rights, Hon Victor Ekwere, who noted the early dilapidation of Awa-Ukam road and Ikot Edehge road in Mkpat Enin less than six months after inauguration.

    According to Hon Ekwere, “I have taken a case study of nine Local Government Areas. So far, out of the 57 roads constructed by this administration, about 97 per cent have failed according to statistics. Maybe because they were made to be trunk A-roads but now turned to trunk C.

    “The Awa -Ukam road was commissioned barely two months on May 29th 2019 but it is now a total mess. I have been receiving calls and I have gone to check the road myself. It is a real mess.”

    In corroboration, the member representing Nsit Atai State Constituency, Rt Hon Mark Esset who said the situation was very pathetic as the bus the committee used during inspection in the area broke down in one of the dilapidated spots wondered why inexperienced construction firms were contracted to carry out the job.

    He drew the attention of the Commissioner to another dilapidated portion of a newly constructed road along Nto-Edino Road in Obot Akara.

    Esset maintained that since it is a road that leads to other States, it should not have been constructed as a trunk C road rather trunk A.

    “You brought in in-experienced construction companies for the Nsit Atai road. The road instead of improving is getting worse. This is unacceptable! Tell those construction companies to leave Nsit Atai road.

    “Whatever we are putting on ground should not be between 2015 to 2023. It should be beyond. It should stand the test of time. In Akwa Ibom, we are not only planning for today, but we are also planning for the future.

    “You will not sit in Executive session to address us. You will be standing on the floor of the House to answer questions. The money Akwa Ibom State Government put on roads, we must receive the value. We can’t take substandard projects in Akwa Ibom State,” Esset said.

    However, Akparawa Ephraim Inyang-eyen, while reacting to the issue of Nsit Atai-Okobo Road project, said it was the Ministry’s set standard and requirement that sent the erring contractors out of the project site.

    He assured that if the current company handling the road fails to meet the set requirements, they would be shown the way out, while government monies would be recovered.

    His words: “Government will not lose money on the Nsit Atai-Okobo Road, be rest assured. Every Kobo will be accounted for. I can say that the governor is committed to dualising that road because we need it as a releasing point for the deep seaport.

    “Out of the 57 major road contracts, 11 have been completed and commissioned. We are very hopeful that by the year 2020, in May when this administration would have been into the first year of the second term, we should be able to deliver at least another 18.”

    From all indications, these were promises that could be extracted for a responsibility.

    Bottlenecks: Another engineer in the ministry of Works doubts if the state government would be able to complete all the roads before 2023. “If care is not taken, the present government may abandon 70 per cent of the roads.

    “There are challenges that impede the completion of the roads. The state government does provide project vehicles for us. Last year, government bought and sent vehicles, but the then Commissioner, Permanent Secretary and some directors collected them without channeling to appropriate offices.

    “Two, compensation is not paid to property. I do not want to go into what transpired between the out-gone commissioner and other contractors.

    “Three, project staffers are not paid their allowances. How do you expect them to supervise the roads even if they assigned?, he said.

    However, Professor Eno Ibanga, the state Commissioner for Works did not want to respond to our text message.

     

     

    Anua-Mbak Etoi-Ishiet Road Chief Godswill Akpabio administration Ikot Esu-Otomo-Ikot Udom-Nto Onono-Azumini Road Ikot Ibritam-Ekeffe-Ikot Akpan Afaha Road Ikot Udom Ika Setraco Tony Opara-manager of ALMADAL NIG. LTD
    Share. WhatsApp Facebook Twitter Pinterest LinkedIn Tumblr Email
    straightnewsng.com
    • Website

    Related Posts

    Akwa Ibom Govt Clears Air on Stubbs Creek land Ownership

    January 7, 2026 --- 9:29 am

    Anambra Declares Chieftaincy Title Conferred on Nigerian Ambassador as ‘Fake’

    January 2, 2026 --- 1:49 pm

    CHRAN Decries Akwa Ibom LG Councils as Poverty Centres

    December 31, 2025 --- 12:11 am

    Comments are closed.

    Search
    Our Picks
    Don't Miss
    Football

    AFCON 2025: Nigeria claim bronze medal After Crushing Egypt on Penalties

    By straightnewsng.comJanuary 17, 2026 --- 9:02 pm0

    By Edi Umoh Nigeria claimed bronze medal at AFCON 2025 in a third place match…

    Consortium Plans to Invest $8 billion in Ibom Deep Seaport

    January 16, 2026 --- 9:02 pm

    Two Scholars Take on Akwa Ibom AG over Stubbs Creek Land Ownership  

    January 16, 2026 --- 4:01 pm

    Reframing Nigeria’s Banditry Crisis: From Assumptions to Reasons

    January 15, 2026 --- 11:22 pm

    Subscribe to Updates

    Get the latest creative news from SmartMag about art & design.

    About Us
    About Us

    The publication is committed to the principles of development journalism. We are prepared to change the public perception that the profession is a harbinger of hate, blackmail, sycophancy, prejudice and falsehood.

    We pledge to use journalism practice to give voice to the voiceless and to give people of all shades of opinions an opportunity to tell their stories.
    We're accepting new partnerships right now.

    Recent Posts
    • AFCON 2025: Nigeria claim bronze medal After Crushing Egypt on Penalties
    • Consortium Plans to Invest $8 billion in Ibom Deep Seaport
    • Two Scholars Take on Akwa Ibom AG over Stubbs Creek Land Ownership  
    • Reframing Nigeria’s Banditry Crisis: From Assumptions to Reasons
    • Inauguration: Catholic Knight Quits over Alleged Non-Acknowledgement of Ubah
    Facebook X (Twitter) Instagram Pinterest
    • Advertise With Us
    © 2026 Straightnews Wire Limited

    Type above and press Enter to search. Press Esc to cancel.